Adey Steel’s scope was to produce a 3D model in Tekla Structures and to fabricate 15 sections of footbridge, stairs and ramp walkways to Network Rail design.
Partial trial assembly of each connecting section without our works ensured that each deck fitted to the next within tolerance. The 87-tonne structure was completed to an extremely tight programme allowing a dangerous level crossing to be upgraded to a safer bridge solution.